JET IP Quarterly Progress Dashboard
Executive Summary
This seventh quarterly progress report covers the quarter ending 30 June 2026, the third year of implementation of the Just Energy Transition Implementation Plan. Implementation continued to advance at a steady pace, with coordination arrangements across the six JET Portfolios becoming increasingly operational and implementation shifting from programme design towards delivery. The defining financial movement of the quarter was the conversion of existing commitments into allocations rather than the arrival of new pledges.
Two different measurement universes are reported below
The JET IP reports finance at two distinct levels. They are not interchangeable and are deliberately shown apart throughout this dashboard.
Instrument level The Financing Status records commitments and allocations at instrument, programme, facility and partner-envelope level.
Project level The JET Investments Register records individual project rows. It is a subset and further decomposition of the Financing Status, not a duplicate of it.
Financing Status Instrument level
JET Investments Register Project level
How the two measures relate
Of the USD 7.276 bn recorded as allocated at instrument level, USD 4.325 bn has been translated into individual project records. The remaining USD 2.951 bn sits at instrument, programme, facility or funder-envelope level and has not yet been decomposed into project rows.
This difference is not an error. It reflects financing assigned at instrument, programme, facility or funder-envelope level, some relating to programmes or facilities still at a planned stage. The ZAR difference of ZAR 52.26 bn (ZAR 128.714 bn less ZAR 76.459 bn) will not equal a flat conversion of the USD difference, because completed project records may retain the historical exchange rates applicable at closure.
Movement over the quarter: 31 March → 30 June 2026
Interpretation. The quarter's principal movement was from existing commitments into allocation, rather than a material increase in new pledges. Commitments rose by USD 18 mn while allocations rose by USD 1.161 bn.
Principal developments in the quarter
- The Joint Appraisal Document for the RESET and MJET programmes was submitted to the Climate Investment Funds at the end of June 2026.
- Credit Guarantee Vehicle preparation advanced from design into capitalisation and institution-building, with implementation structures in place and ITP pipeline alignment confirmed.
- The Municipal Portfolio reconstituted its workstreams following the strategy meeting (1 June 2026) and established dedicated technical delivery capacity led by the JET PMU.
- Eskom commissioned 76 chargers across 55 sites between March and June 2026, adding approximately 191 charging points to the national network.
- The PtX PDS Green Hydrogen Project Screening Tool was launched on 19 May 2026 at the World Hydrogen Summit.
- Funding Platform cumulative matches rose from five to nine; 171 Expressions of Interest were received under Window 3.
- The CIF Secretariat requested technical clarifications on the JAD. Trust Fund Committee review and approval had not been obtained by 30 June 2026.
- The ITP Phase 1 RFP, scheduled for June 2026, had not been issued by 30 June and no revised issue date was confirmed.
- The CGV had not yet been registered or launched; final capital commitments, regulatory licensing and company incorporation remained outstanding.
- The Mpumalanga JTCC did not meet during the reporting quarter.
- The National JET Skills Advisory Forum did not convene; its next meeting was scheduled for 4 September 2026.
- Highly concessional loans of USD 450 mn remain wholly unallocated, pending finalisation of ACT IP implementation arrangements.
The six formal JET Portfolios at a glance Project level
| Portfolio | Projects | USD mn | ZAR mn |
|---|
Source: Q2 2026 Report (Final for Approval, v3), Table 5 (counts) and Tables 6–11 (values). Energy Efficiency and Road to Rail are additional registered investment categories and are not formal JET Portfolios; they are reported in the Portfolio Progress tab.
JET Financing Status Instrument level
JET financing is entering a phase in which the emphasis is shifting from mobilising commitments towards translating financing instruments, programmes and facilities into implementation-ready and registered projects. Everything on this tab is measured at instrument level. Project-level registered investment is reported separately under Portfolio Progress.
What “allocated” means in this report
Financing assigned at instrument, programme, facility, partner-envelope or named-project level as recorded in the Financing Status.
Allocation is not evidence of disbursement, expenditure, financial close, implementation commencement, or the existence of an individual project record in the JET Investments Register.
Financing position as at 30 June 2026
Composition of the inclusive total
Labelling control. The USD 14.382 bn figure is the inclusive grand total. It is not composed solely of international partner pledges. Per Table 3, it comprises USD 13.177 bn of international partner, sovereign bilateral and MDB commitments plus USD 1.205 bn of Private Sector and Local DFI commitments.
Q1 → Q2 movement
The quarter's movement was driven almost entirely by the allocation of commitments already recorded, rather than by new pledges. The principal allocation movements were: Other Guarantees, where the United Kingdom's allocation rose from USD 87 mn to USD 487 mn; concessional loans, up USD 702 mn (USD 324 mn France, USD 378 mn EU/EIB); and grants, up USD 60 mn, including USD 50 mn recorded as allocated by the Climate Investment Funds. Together these account for the USD 1.161 bn increase, subject to rounding.
A further USD 330 mn of planned Local DFI concessional loan financing was added to the inclusive concessional total during the quarter. It represents anticipated leveraged financing from local DFIs, included in the Climate Investment Funds pledges under the ACT-IP package; it is recorded as planned and does not represent a committed amount.
Position by financing instrument
Percentages are stated on the inclusive basis. Where an international / sovereign / MDB rate also exists, both are shown and the denominator is labelled.
Allocation rate by instrument Instrument level
| Instrument | Pledged USD mn | Allocated USD mn | Inclusive rate | Intl / MDB rate | Pledged ZAR mn | Allocated ZAR mn |
|---|---|---|---|---|---|---|
| Inclusive grand total Calculated from unrounded source data; rows may not add exactly. |
14 382 | 7 276 | 50.6% | 55.2% on USD 13 177 |
254 409 | 128 714 |
Scoped denominators. Concessional loans: 48.1% inclusive (on USD 3 863 mn) or 52.6% on the international / sovereign / MDB basis (on USD 3 533 mn, excluding the USD 330 mn of planned Local DFI financing). Commercial debt, equity and guarantees: 7.0% inclusive (on USD 4 036 mn) or 9.0% on the international / MDB basis (on USD 3 161 mn, excluding the USD 875 mn of planned Private Sector financing).
Spain's USD 2.268 bn envelope remains unallocated pending activation of the underlying deployment mechanisms.
Comparison with the original 2021 IPG Political Declaration
Original 2021 IPG pledge
Current inclusive total
This is not a like-for-like comparison. The current inclusive total includes additional international partners, sovereign bilateral partners, multilateral development institution commitments, Private Sector commitments and Local DFI commitments that did not form part of the original declaration. The increase must not be read as if the membership or scope had remained unchanged.
New-generation financing mechanisms
Credit Guarantee Vehicle (CGV)
Intended to become the principal risk-sharing mechanism supporting private investment in electricity transmission through the Independent Transmission Programme. By 30 June 2026, preparation had advanced from design into capitalisation and institution-building, with implementation structures in place and ITP pipeline alignment confirmed.
Not yet registered Final capital commitments, regulatory licensing and company incorporation remained outstanding at the reporting cut-off.
Municipal Utility Reform Programme (MURP)
Combines concessional finance, guarantees and institutional reforms to improve municipal creditworthiness and make municipal infrastructure projects increasingly investable. Currently supported through the United Kingdom guarantee facility.
In progress Has not yet been reflected as individual projects in the JET Investments Register.
Next major financing milestone. Deployment of the USD 450 mn highly concessional financing package under the ACT Investment Plan, particularly through the RESET and MJET programmes. This envelope remained wholly unallocated at 30 June 2026.
Source: Q2 2026 Report (Final for Approval, v3), Section 3, Tables 1–3. ZAR equivalents converted at USD 1 = ZAR 17.69, the currency-pair average for the quarter ending 30 June 2026. Minor differences may arise from rounding.
Portfolio Progress Project level
Everything on this tab is measured at project level from the JET Investments Register. These values are a decomposition of the wider instrument-level Financing Status and are not interchangeable with it.
There are exactly six formal JET Portfolios. Energy Efficiency and Road to Rail are additional registered investment categories included in the Register for reconciliation and reporting completeness. They do not expand the official number of JET Portfolios beyond six and are shown separately below.
Total project records
Registered investment
Implementation + completed
Six formal portfolios
JET Investments Register by status Project level
| Status | Projects | Share of projects | USD mn |
|---|---|---|---|
| A. Planned | 22 | 8.3% | 529 |
| B. Approved | 20 | 7.5% | 324 |
| C. Implementation Phase | 127 | 47.7% | 2 502 |
| D. Completed | 97 | 36.5% | 969 |
| Total | 266 | 100.0% | 4 325 |
Counts from Table 5; values from Table 4. Sub-totals are calculated from unrounded source data, so visible row values may not add exactly. Project counts and investment values are complementary measures and should be interpreted independently: projects in implementation are 47.7% of records but 57.9% of value.
The six formal JET Portfolios
Additional registered investment categories
Combined: 9 project records, USD 63 mn, ZAR 1.11 bn — 8 in implementation and 1 completed.
Registered investment by formal portfolio Project level
Electricity, Green Hydrogen and Municipalities together account for USD 3.912 bn, or 90.5% of the total project-level Register value of USD 4.325 bn. Measured against the six-formal-portfolio sub-total of USD 4.262 bn, the same three portfolios account for 91.8%.
Project records by formal portfolio
Electricity Portfolio
The portfolio focuses on mobilising financing for two priority areas: transmission infrastructure upgrades and expansion to enable large-scale grid uptake of renewable energy; and the ACT Investment Plan for repowering, repurposing, community development and decommissioning of the five Eskom coal power stations that IRP 2025 has scheduled to close by 2030 — Camden, Hendrina, Grootvlei, Arnot and Kriel.
Project records Project
Registered investment Project
In implementation
Completed
Two different financing figures — do not conflate them
Instrument level USD 3.863 bn (ZAR 68.336 bn) is the JET-wide inclusive concessional-loan total recorded in the Financing Status (Section 3 / Table 3). It includes USD 330 mn of planned Local DFI concessional financing that has not been formally committed or legally secured. It is not this portfolio's registered investment and must not be read as an amount available for Eskom or NTCSA to borrow.
Project level USD 3 124.70 mn (ZAR 55 232.70 mn), approximately USD 3.125 bn across 75 projects, is the Electricity Portfolio's registered investment in the JET Investments Register (Section 4.1 / Table 6).
Note: Section 4.1 of the report does not cite the concessional-loan total. It is shown here only as a reconciliation control against the instrument-level Financing Status.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Transmission
The DEE, in partnership with National Treasury, is enabling private sector participation in the transmission grid through the Independent Transmission Programme. To derisk this private investment, National Treasury and the World Bank Group are preparing the Credit Guarantee Vehicle.
Independent Transmission Programme — position at 30 June 2026
Phase 1 procurement was initially scheduled for June 2026. Owing to delays, the final Request for Proposals had not been issued by 30 June 2026, and a revised issue date had not been confirmed. Transmission procurement remained the most significant implementation constraint during the reporting period.
Decommissioning under the ACT Investment Plan — RESET and MJET
The Eskom Board resolved in May 2024 to delay decommissioning of Camden, Grootvlei and Hendrina until March 2030, necessitating updates to the ACT Investment Plan, which had originally projected associated emissions reductions of 71 Mt CO₂ by 2030. The Updated ACT IP was approved by the CIF Trust Fund Committee in June 2025.
Period control. CIF approval is not complete. At 30 June 2026 the programmes were still awaiting Trust Fund Committee review and approval.
Credit Guarantee Vehicle and the ACT Desk
Credit Guarantee Vehicle
- Design advanced into capitalisation and institution-building
- Implementation structures in place
- Alignment with the ITP pipeline confirmed
- Final capital commitments outstanding
- Regulatory licensing outstanding
- Company incorporation outstanding
Not registered or launched
ACT Desk and implementation architecture
The ACT Desk within the JET PMU is being operationalised to support programme coordination, ensure compliance with CIF timelines and MDB processes, and align reporting across national and international frameworks. Short-term funding has been secured for the establishment of the ACT Desk within the JET PMU in 2026. As reported at 31 March 2026, funding had been secured for a year and the Desk's structure confirmed; this is carried forward as cumulative context.
Implementation is structured through a multi-phase approach combining infrastructure interventions — repowering through renewable energy PPPs at each site — with a strengthened socio-economic transition focus through MJET.
Portfolio composition
By intervention type
Financing instrument concentration
Policy loans and concessional loans together account for approximately 86% of total portfolio value (USD 2.69 bn / ZAR 47.52 bn), reflecting a strategic focus on large-scale sector transformation, infrastructure development and policy reform through public financing mechanisms.
At the same time the portfolio includes a large number of grant-funded interventions, with grants accounting for 60 of the 75 activities (80%). Grants primarily support technical assistance, capacity development, studies and research, and targeted infrastructure activities.
More than 90% of portfolio value is either under implementation or completed, reflecting the maturity of the portfolio.
Source: Q2 2026 Report (Final for Approval, v3), Section 4.1 and Table 6. Project status and investment values: Table 6. Concessional-loan total (reconciliation control): Section 3 / Table 3. JAD, Credit Guarantee Vehicle, Independent Transmission Programme and ACT Desk status: Section 4.1 narrative, with Section 2 and Table 12. This tab reflects the 30 June 2026 position only; no later portfolio-lead updates are included.
JET Municipal Portfolio
JET investments in electricity distribution infrastructure are driven within this portfolio. Municipalities are increasingly central actors in the energy transition — in embedded generation, electricity distribution, energy efficiency and resilient local infrastructure — but weak municipal balance sheets and constrained borrowing capacity continue to limit investment.
Project records Project
Registered investment
In implementation
Completed
Governance was materially restructured during the quarter
The JET Municipal Council met on 31 March 2026. A strategy meeting was convened on 1 June 2026 to reorient the programme and refocus implementation priorities. Governance is not unchanged from Q1.
Outcomes of the strategy meeting (1 June 2026)
- The programme approach was reviewed
- Workstreams were reconstituted and streamlined
- Dedicated technical delivery capacity was established, led by the JET PMU in collaboration with the relevant institutions.
- Agreement to develop a programme dashboard as the primary performance monitoring and reporting tool
- Workstream meetings were temporarily paused during the review and restructuring
Revised division of responsibility
Retained under SALGA: governance and coordination functions, including coordination of the JET Municipal Council, communications and stakeholder engagement.
Led by the JET PMU: day-to-day technical implementation of the programme, in collaboration with the relevant lead institutions.
The separation is expected to strengthen accountability, improve operational efficiency and clarify roles and responsibilities across the programme.
Workstreams meeting before the pause: Capability Development (3 February 2026), Energy Access (4 February 2026), Finance (4 March 2026).
Programmes and pipeline
MURP — Municipal Utility Reform Programme
UK and AfDB-funded, launched in late 2025, piloting institutional and financing reforms in four Mpumalanga municipalities. Aims to channel concessional and private investment into municipal water and electricity infrastructure, leveraging the UK guarantee facility for AfDB lending. Not yet reflected as individual projects in the JET Investments Register.
MDxJET — Municipal Distribution Just Energy Transition
German IKI-funded initiative beginning in Q2 2026, supporting 20 municipalities over three years to develop capacity and project plans for investment in modernising distribution infrastructure in preparation for the wholesale electricity market and other reforms.
Technical Delivery Function
Operationalised Fully operationalised to support implementation of the IKI programme and the development and coordination of the Integrated Municipal Energy Access workstream, strengthening technical oversight and delivery.
Integrated municipal energy access pipeline
Under development to provide a consolidated view of energy access initiatives across municipalities, bringing together projects from MDxJET, Mission 300, MJET under ACT, INEP and other initiatives. Supports national electrification objectives across rooftop solar, mini-grids, micro-grids and other distributed energy solutions.
During the reporting period the portfolio continued building a municipal JET project pipeline, beginning with the top 20 electricity-distribution licensed municipalities, covering grid refurbishment, loss reduction, embedded generation integration and electrification. In parallel, work began on mapping project preparation efforts with applicable funding modalities and eligibility requirements. Initial engagements were held with National Treasury and the DBSA on the design of a municipal funding model for electricity distribution infrastructure, and the first five priority municipalities were identified for piloting the model.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Technical Assistance accounts for the largest number of projects (17; 52%), followed by Infrastructure (6; 18%) and Capacity Development and Training (5; 15%), with studies and research (3; 9%) and project preparation (2; 6%). The portfolio is predominantly grant-funded, with 31 of 33 projects financed through grants. However, a significant share of value is provided through loan-based and blended instruments: one concessional loan of USD 129.6 mn (ZAR 2.29 bn), the largest single financing instrument in the portfolio, and one Other Guarantees investment of USD 86.7 mn (ZAR 1.53 bn). These are project-level values recorded in the JET Investments Register; they are not the instrument-level concessional-loan and Other Guarantees totals reported under Financing Status.
Source: Q2 2026 Report (Final for Approval, v3), Section 4.2. Project status and investment values: Table 7. Financing-instrument classification and portfolio composition: Section 4.2 narrative.
Mpumalanga Just Transition Portfolio
The Just Transition Coordination Committee is chaired jointly by the Department of Economic Development and Tourism and the Department of Agriculture and Rural Development, Land and Environmental Affairs, with the Mpumalanga Green Cluster Agency as Secretariat. Steps are underway to strengthen the MGCA's capacity for JET, maintain an online register of Mpumalanga JET projects, and manage monitoring and evaluation under the JET PMU's national MEL system.
Project records Project
Registered investment
In implementation
Completed
Governance position at 30 June 2026
The Mpumalanga Just Transition Coordination Committee did not meet during the reporting quarter. The report records that the JTCC has not met this year. A strategic workshop is planned to address this in Q3 2026.
The Provincial Leadership of SAFTU, FEDUSA and COSATU have been invited to the Mpumalanga JTCC but do not attend.
Verification qualification retained. No new Mpumalanga JET projects were planned during Q2 2026, and records held by the Mpumalanga Green Cluster Agency remain subject to verification and are not yet reflected in the Register.
Community ownership objective
Level 5 community ownership target
The portfolio aims to have at least four community-owned projects (Level 5) by year-end, structured through trusts or community partnership agreements that embed ownership and long-term benefit-sharing. Community co-design (Level 3 or higher) is a requirement for relevant projects.
Of the nine projects matched through the JET Funding Platform, two are community-owned at Level 5 and one is at Level 4, with the remainder under review for final grading. Forty percent of relevant matched projects on the register have achieved a Level 3 engagement score or higher.
Reconciliation qualification. Table 12 states that “the remaining 5 projects are under review for final grading”, which together with the two Level 5 and one Level 4 projects arithmetically accounts for only eight of the nine matched projects. This tab therefore uses the Section 2 formulation, the remainder under review. Table 12 is reproduced verbatim and uncorrected in the Milestones register.
Three Calls for Proposals are planned during 2026 to develop a pipeline of community-led and community-owned projects.
Grootvlei Climate Smart Horticulture Centre
Launched 27 January 2026 at Grootvlei Power Station through a partnership between Eskom, the Government of the Netherlands, the MGCA and other implementation partners. Established on repurposed power station land, the Centre promotes economic diversification through climate-smart horticulture, skills development and agripreneurship. It includes a 0.5-hectare demonstration greenhouse within a broader 20-hectare horticulture and agribusiness development programme.
During the reporting period: eight community members were trained as greenhouse facilitators and 75 local agripreneurs were enrolled in the Agripreneur Development Programme.
SAJJOF-supported activities during the quarter
The AfDB South Africa JET Jobs First Project supported practical gender and social inclusion interventions in Mpumalanga.
- Digitisation of the Mpumalanga Premier's Youth Development Fund, with consultations with the Office of the Premier and SITA, and finalisation and advertising of Terms of Reference
- Alignment of the digitisation with the provincial Livi Lemphakatsi citizen engagement application
- Review of the 2012 Provincial Skills Strategy and development of a provincial skills masterplan and action plan
- Support to the Gender Desk within MGCA to strengthen coordination, reporting and project preparation for women's empowerment initiatives
- 25 rural women farmers supported through training, seed funding, data access and connectivity, coaching and mentoring, and linkages to off-taker opportunities and formal value chains
- Household sustainable livelihood work advanced through DSD — business case submitted, beneficiary lists drafted and costed, procurement plans developed
- Inclusive social business and microfinance programme progressed with DSD, NASASA, the Nelson Mandela Children's Fund and NAFCOC; a provincial conference is planned for Nkangala District Municipality in October 2026
- The ILO / ITCILO training programme was completed, delivering Just Transition, green business development, resilience and training-of-trainers support
- SAJJOF Phase 2 preparation progressed through appointment of BCG, stakeholder consultations, site visits and finalisation of the business plan for submission to AfDB
Social Employment Fund. The SEF programme, valued at ZAR 150 million, funded by National Treasury and to be implemented by the Industrial Development Corporation, was matched through the JET Funding Platform during the quarter.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Funding is predominantly grant-based, with 65 of the 66 projects financed through grants (approximately USD 146.8 mn / ZAR 2.60 bn). The exception is a commercial debt/equity investment in Agristar Holdings from the United Kingdom, valued at USD 13.6 mn (ZAR 241 mn). Studies and Research (29%) and Community Organisational Development (26%) comprise over half the portfolio, followed by Technical Assistance (14%), Capacity Development and Training (11%) and Socio-economic Investments (11%). Infrastructure accounts for 6%, with Project Preparation (3%) and Communication (2%).
Source: Q2 2026 Report (Final for Approval, v3), Section 4.3 and Table 8. Project status and investment values: Table 8. Institutional arrangements, projects pipeline, SAJJOF activities and portfolio composition: Section 4.3 narrative, with JTCC, verification, community-ownership and Social Employment Fund status from Section 2 and Table 12. This tab reflects the 30 June 2026 position only; no later portfolio-lead updates are included.
New Energy Vehicles Portfolio
The NEV Portfolio expanded its governance architecture materially during the quarter while remaining, in project-register terms, at an early stage of development with the majority of value concentrated in planned projects.
Project records Project
Registered investment
Chargers commissioned
Charging points added
Governance developments during the quarter
Workstream meetings
The PMO held its second workstream meetings for the Public Transport workstream (chaired by DBSA, 15 May 2026) and the Shared Charging Infrastructure workstream (chaired by Eskom Distribution, 11 May 2026), introducing its action-plan approach to consolidating and identifying projects.
NEV Skills and Training Forum
Launched May 2026 Launched with NBI, AIDC, AIDC–EC, uYilo, Green Cape, RMI, TASEZ, TIPS, GIZ and NAACAM. To be co-chaired by AIDC and NAACAM, focusing on implementing skills-related initiatives.
JET NEV Technical Task Team
The NECOM e-mobility workstream has been incorporated into the JET IP NEV structures and will be known as the JET NEV Technical Task Team, focusing on shared charging infrastructure standards, regulations and technical expertise. It will form part of the Shared Charging Infrastructure Platform as its technical advisory committee.
Battery Value Chain Platform
Kick-off meeting held May 2026. A steering committee was established comprising DEE, the University of the Western Cape, SABS and the DTIC, overseeing workstreams on policy development, technical standards and regulations, project development, applied research and market access.
Project Developers Forum
In planning The PMO is establishing a Charging Infrastructure and Mobility Project Developers Forum to provide a formal platform for industry to consolidate proposals, issues and barriers for consideration by government, policymakers and regulators. Recruitment for a NEV policy specialist is underway.
Looking ahead
The PMO will host the second JET NEV Advisory Committee meeting, co-chaired by DoT and the DTIC, in the next quarter.
Charging infrastructure
The PMO has set a target of approximately 200 charge points per annum, or 400 installed by the end of 2027.
Eskom deployment, March to June 2026
Eskom installed 76 chargers at 55 sites, adding approximately 191 charge points. Twelve of the 55 commissioned sites are publicly accessible for EV drivers. Eskom has spent close to ZAR 52.8 million for this phase. This is Eskom's second round of charging infrastructure investment.
Off-grid N3 corridor sites
In May 2026, Charge (formerly Zero Carbon Charge) launched two off-grid, solar-powered charging sites on the N3 corridor: Charge N3 Roadside at the Reitz Interchange in the Free State, and Charge N3 Tugela at the Colenso–Winterton Interchange in KwaZulu-Natal. Each site has eight charge points and operates entirely off-grid using solar generation and battery storage, serving both private cars and logistics vehicles.
No significant progress was reported on the deployment of electric buses during the quarter. Johannesburg, in partnership with C40, is piloting electric bus trials with Rea Vaya, Metrobus and several OEMs for a limited period; the tender closed on 23 February 2026.
Funding and pipeline — Q2 2026 developments
Funding mobilisation continued towards the annual target of ZAR 200 million.
Cumulative context carried forward in the Q2 2026 Report (Final for Approval, v3)
The IDC's approval of ZAR 96 mn for Thula Solutions and the City of Johannesburg's allocation of ZAR 12 mn to its electric vehicle programme were reported in the quarter ended 31 March 2026 and are carried in the Q2 report as cumulative context, not as new Q2 movements.
An investment of USD 750 million in Nyanza Light Metals, a titanium dioxide pigment project in the Richards Bay IDZ, will support production of battery-grade iron phosphate. The project is currently at bankable feasibility study phase, expected to be completed in 2028.
A concept note for an NEV funding programme has gone to market and the PMO is seeking funding partners. An application to the Mitigation Action Facility was unsuccessful; engagements with other potential funders and climate funds are ongoing.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Four planned projects account for 97% of total investment value; the largest investments remain in the pipeline. Six out of eight projects (75%) are dedicated to Studies/Research and Technical Assistance; two infrastructure projects (25%) indicate initial progress towards implementation. The portfolio reflects an emerging investment area with significant future growth potential.
Source: Q2 2026 Report (Final for Approval, v3). Project status and investment values: Table 9. Portfolio composition, governance, charging infrastructure and funding developments: Section 4.4 narrative, with cumulative context and electric-bus status from Section 2 and Table 12. This tab reflects the 30 June 2026 position only; no later portfolio-lead updates are included.
Green Hydrogen Portfolio
In 2026 the portfolio is completing pre-feasibility and feasibility studies for two export projects and one domestic project, laying the groundwork for investment-ready interventions that can move to implementation. Coordination structures are being operationalised and funding flows from existing grant pledges are being tracked through the JET Investments Register.
Project records Project
Registered investment
Planned
In implementation
Institutional arrangements
The recruitment process for the GH2 Policy Specialist was finalised in Q2. A secondee was deployed to the Department of Electricity and Energy on 1 May 2026 to chair the two DEE-led workstreams, Policy and Regulations and Community Engagement. Discussions are underway to consolidate the Supply and Demand workstream, currently chaired by the DTIC, into the Policy and Regulations workstream, centralising policy-related activities and streamlining development of the green hydrogen policy and regulatory framework.
Five workstreams have held inaugural meetings: Finance (IDC, 24 March 2026); Shared Infrastructure (IDC, 19 January 2026); Technology Incubation and Workforce (DHET, 20 February 2026); Community Engagement (DEE, 10 March 2026); and Policy and Regulations (DEE, 10 March 2026). The GH2 Advisory Committee met on 24 February 2026 and the Project Developers Forum on 17 February 2026. The Finance workstream last met on 18 June 2026.
PtX PDS Green Hydrogen Project Screening Tool
At the World Hydrogen Summit exhibition, South Africa showcased its green hydrogen value proposition through a national pavilion highlighting the country's renewable energy potential and export ambitions, facilitating strategic engagements with investors, developers, government representatives, DFIs, technology providers and international partners.
Feasibility study status — no change recorded
The status of the green hydrogen feasibility studies was unchanged from the previous quarter. One PtX project has received funding for bankability feasibility, in addition to the three projects reported at the end of December 2025, giving a cumulative four PtX projects that have received funding to progress to the next phase. Completion of the pre-feasibility and feasibility studies for two export and one domestic project must not be inferred.
There were no material changes to Green Hydrogen funding flows during the quarter. A EUR 7 mn grant will be funded through AFD in 2026 to support Transnet towards green hydrogen projects. While grant funding targets were exceeded, the loan target was not met. The SAH2 Fund remains in development.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Source: Q2 2026 Report (Final for Approval, v3), Section 4.5 and Table 10. Project status and investment values: Table 10. Institutional arrangements, screening tool and portfolio context: Section 4.5 narrative, with workstream meetings and feasibility and funding-flow status from Section 2 and Table 12. This tab reflects the 30 June 2026 position only; no later portfolio-lead updates are included.
JET Skills Portfolio
The portfolio supports a coherent and coordinated skills system responding to evolving demand from the energy transition in support of economic diversification. The work of the JET Skills Desk at DHET and the multi-stakeholder National JET Skills Advisory Forum convened by the Human Resources Development Council continues. A next step is finalisation of the JET Integrated Skills Plan.
Project records Project
Registered investment
In implementation
Completed
Governance position at 30 June 2026
The National JET Skills Advisory Forum did not convene during Q2 2026. Its next meeting was scheduled to take place on 4 September 2026, which falls in Q3. In the interim, the Skills Portfolio Secretariat continued to meet to prepare for the upcoming Forum session.
Skills Development Zone pilot — preparatory phase
Progress towards establishing the first Skills Development Zone pilot in Mpumalanga remained slower than planned. As at 30 June 2026:
- The pilot had not commenced operations
- The anchor institution had not been identified
- The partnership agreement had not been signed
- Baseline trainee data had not yet been collected
In February 2026 the JET Skills Desk drafted an implementation workplan for the first Skills Development Zone, and work is under way to agree priority areas of work and funding requirements. Launch of the pilot remains scheduled for Q4 2026. Future milestones must not be presented as completed.
Institutional arrangements
The Presidency and DHET MOU defines the systems and institutional arrangements driving implementation. The JET Skills Desk (Secretariat) was established by DHET and located in the Office of the Director General, and the HRDC convenes the multi-stakeholder National JET Skills Advisory Forum. The NEV Workforce and Skills workstream and the Green Hydrogen Technology Incubation and Workforce Skills workstream were established in February 2026, with work underway to align and integrate skills provisioning to sectoral industrial development strategies. The EU, Germany and Switzerland are supporting implementation, with EUR 15 mn from the EU allocated to strengthen TVET and skills development institutional systems.
Projects pipeline
JET Skilling for Employment Programme (JET SEP)
Led by the National Business Initiative to drive a coordinated, multi-sector, demand-led approach to JET skills development. Awarded a USD 1 mn (ZAR 17.70 mn) grant through the Fund for African Private Sector Assistance to finance Phase 1, scheduled between 1 April 2025 and 31 May 2026.
A second phase is being funded by the Canadian government, with CAD 5 mn (USD 3.75 mn / ZAR 66.38 mn) recorded for Phase 2 of the JET SEP Programme.
Regional mapping and the JET Labour Centre
Regional mapping has commenced in Mpumalanga, the Eastern Cape and the Northern Cape to identify existing catalytic skills programmes and the practical gaps requiring resourcing, and to map regional skills plans and the baseline of existing skills provisioning.
The JET Labour Centre has received initial grant funding and is defining a skills programme of action for organised labour.
The JET Skills Desk has presented its Technical Implementation Plan (2025–2030) to 11 SETAs, with work underway to coordinate and streamline reporting against national targets.
Portfolio status Project level
| Status | Projects | USD mn | ZAR mn | Share of value |
|---|
Approximately 41% of projects are dedicated to studies and research, 34% support capacity development and training, and 16% provide technical assistance. The remaining 9% is distributed across communication initiatives, community organisational development, infrastructure development and socio-economic investments.
Source: Q2 2026 Report (Final for Approval, v3), Section 4.6 and Table 11. Project status and investment values: Table 11. Institutional arrangements, projects pipeline and portfolio composition: Section 4.6 narrative, with Forum, Skills Development Zone and regional-mapping status from Section 2 and Table 12. This tab reflects the 30 June 2026 position only; no later portfolio-lead updates are included.
JET Funding Platform
The JET Funding Platform is a match-making service offered by the JET PMU to bring together providers of JET grant funding with intended JET constituents, and to assist constituents in preparing project applications. Launched on 25 October 2024, it is supported by an Advisory Committee of nine experienced individuals who provide strategic advice without decision-making powers.
Cumulative matches
Window 3 EOIs received
Projects on the Register
Investment-readiness cohort
Window 3 — Jobs and Livelihoods
24 Feb 2026
April 2026
received
under adjudication
the Register
Reporting control. The report records 171 Expressions of Interest received and shortlisted applications under adjudication during the reporting period. It does not state how many applications passed each intermediate stage, and no such figures are inferred here. Following the first two windows, analysis revealed challenges with funder-project alignment and due diligence, prompting a strategic shift towards more curated, theme-specific application windows in 2026.
Completed during Q2 2026
In development at the reporting cut-off
Funder Portal Q3 2026
Seed funding secured for development of the Funder Portal and digital grants register. Portal development is scheduled to commence in Q3 2026 and had not begun at the reporting cut-off. Seed funding was secured in the quarter ended 31 March 2026 and is carried here as cumulative context.
Pooled Fund Pilot in development
Development of a Pooled Fund pilot is underway. Draft commercial terms had been prepared and fund hosting arrangements were under consideration during the quarter. The Pooled Fund is intended to reduce transaction costs and enable more flexible, aligned support for priority Just Transition interventions.
Two further windows In development
A further two application windows remained in development for 2026 at the reporting cut-off.
2026 Register target In progress
The Platform is targeting 50 grant-ready, credible, high-impact projects on the Register by end 2026, against 26 at 30 June. The next cohort will enter the Register upon completion of the Window 3 adjudication. The matched-funded conversion rate is being improved by 25% through a streamlined funder engagement model.
Project preparation support. Project Preparation funding has been secured until end 2027. Two project preparation support partners were onboarded in Q1 2026. Resources have been secured to develop and implement the Funding Platform Advocacy and Engagement strategy, and the stakeholder database is being actively grown.
Disaggregated beneficiary reporting. Work is ongoing regarding receipt of reporting for existing projects; this will extend to new projects brought onto the Register in 2026.
Source: Q2 2026 Report (Final for Approval, v3), Section 5, with Section 2 and Table 12 (STO4). Forward-looking items above are shown as at 30 June 2026 and must not be read as completed.
JET Governance
Governance and coordination arrangements continued to evolve across the JET Portfolios during the reporting period. Lead institutions and portfolio secretariats remained in place, with active coordination in the Electricity, Green Hydrogen and New Energy Vehicles portfolios, a governance review and restructuring in the Municipal portfolio, and two portfolio structures that did not convene during the quarter.
JET Inter-Ministerial Committee
JET Government Steering Committee
Forward position, not a completed event. The next meetings of the IMC and the GSC were both scheduled to take place during September 2026 as at the 30 June 2026 cut-off. Neither had occurred at the reporting date and neither is represented here as completed.
IMC composition
- Minister of Electricity and Energy (Chairperson)
- Minister of Finance
- Minister of Forestry, Fisheries and Environment
- Minister of Mineral and Petroleum Resources
- Minister of Trade, Industry and Competition
- Minister of Cooperative Governance and Traditional Affairs
- Minister of Higher Education and Training
- Minister of Science and Innovation
- Minister of Transport
- Minister of International Relations and Cooperation
- Premier of Mpumalanga Province, as attendee to the JET IMC
Differentiated governance position across the six portfolios
Governance activity was not uniform across the portfolios during Q2 2026. Two structures did not convene.
2026 milestone. A key milestone for 2026 is to ensure that governance and coordination structures across all six JET Portfolios remain fully operational and effectively support implementation. Two structures — the Mpumalanga JTCC and the National JET Skills Advisory Forum — did not convene during the quarter.
Source: Q2 2026 Report (Final for Approval, v3), Section 6 (IMC, GSC and IMC composition), with portfolio governance positions from Sections 2 and 4 and Table 12 (STO2). Forward-looking meetings are shown as at 30 June 2026 and must not be read as completed.
Milestones
Progress against the December 2026 milestones of the JET IP Theory of Change, as reported in Section 7 / Table 12 of the Q2 2026 Report (Final for Approval, v3). Every status shown is the report-controlled Section 7 classification recovered from the source table. No status is derived from narrative wording, and no overall outcome-level rating is calculated.
2026 Milestone Pulse
43 milestones carry one Table 12 status; one governance milestone is subdivided by portfolio in the source. Context figures above are counts, not performance ratings. No score, index, average or weighted rating is calculated anywhere on this tab.
Section 7 status key — select a status to filter
Grey, Red and Violet are part of the controlled Section 7 scheme and are shown for completeness. None occurs in Table 12 at 30 June 2026. This is not a bad-to-good scale: Blue and Violet are completion classifications, and Dark green means on track — neither is “better” or “worse” than the other.
Outcome map — how the 11 outcomes compare
Each marker is one December 2026 milestone carrying its own recovered Table 12 status. A split marker denotes a milestone that is subdivided in the source. These are distributions of underlying source statuses — no overall STO or MTO rating exists or is implied.
Short-term outcomes · capacity and systems, 1–3 years
Medium-term outcomes · behaviour and performance, 3–5 years
Management attention
Surfaces the milestones the source classifies as Red, Orange or Light green. These are the report’s own classifications reproduced mechanically — no dashboard risk judgement has been added.
Milestone explorer — full source detail
Source methodology and provenance
How these statuses were recovered. Section 7 cell fills were originally read directly from the PDF content stream of the earlier Rev 1.5.3 report, pages 34–43, and cross-validated against a 300 dpi raster of the same pages, with full agreement. For this version, the Stage 1 Reconciliation Matrix (Table 12 Milestone Audit) records that the Table 12 progress-cell shading of the Q2 2026 Report (Final for Approval, v3) matches all 44 milestone status categories; no status has been changed. No status was inferred from narrative wording, and no portfolio-analysis rating was used.
36 distinct source colour groupings underlie the 44 milestone records in the Rev 1.5.3 PDF. This is an audit measure of how that source table was encoded, not a milestone denominator. Two effects explain the difference: several single coloured cells span more than one milestone row — one light-green cell covers the first three STO1 milestones — and the STO2 portfolio-coordination milestone contains four separately coloured source sub-blocks.
Two palettes exist and are kept apart. The Section 7 legend swatches on page 34 of the Rev 1.5.3 PDF (Grey #888A8D, Red #E91C23, Orange #FAA61A, Light green #C1D82F, Dark green #79A342, Blue #009FBD, Violet #BD7AB4) are used as the single coherent key throughout this dashboard. The Table 12 body cells are encoded with different values (Dark green #3A7C22, Light green #92D050, Orange #FFC000, Blue #0B769F); the Stage 1 Reconciliation Matrix records the same body-cell values for the v3 Table 12. They are retained in the data layer as provenance evidence only and are never used as UI colours.
Source reconciliation notes affecting this tab
Financing figures inside Table 12. The MTO1 and MTO2 rows reproduce the report's own milestone progress statements verbatim. The total-pledged statements now agree with Section 3 / Table 3 (USD 14.382 bn inclusive; USD 13.177 bn international partners, sovereign bilateral and MDBs). The MTO1 concessional-loan statement retains its Table 12 reporting context of USD 1 156 mn (ZAR 20.44 bn, 66.8% of the ZAR 30.6 bn milestone). This differs from the USD 1 858 mn concessional-loan allocation in Section 3 / Table 3; the Executive Summary records that allocation as having risen from USD 1 156 mn to USD 1 858 mn during the quarter. The Financing Status tab uses Section 3 / Table 3 as the controlling financing source. The difference is recorded in the Source Reconciliation and Decision Log rather than silently corrected here.
Community-ownership count (STO3). Table 12 states that “the remaining 5 projects are under review for final grading”. Together with the two Level 5 and one Level 4 projects, this arithmetically accounts for only eight of the nine matched projects. The Mpumalanga JT tab therefore uses the Section 2 formulation, the remainder under review. Table 12 is reproduced above verbatim and uncorrected.
Other dedicated-section differences. Table 12 also differs from the dedicated narrative and portfolio sections on the Investments Register expansion timing (early 2027 retained here; Section 2 states Q3 2026), the Zimi Charge charge-point wording (Section 4.4 refers to charging stations), the grant funds spent on completed projects (USD 104.634 mn and 12% here; Section 2 states USD 104.635 mn and 11.9%), and Eskom spend of ZAR 52.6 mn (Section 4.4 states ZAR 52.8 mn). In each case the dedicated section governs its own dashboard tab and Table 12 is preserved verbatim here. All are recorded in the Source Reconciliation and Decision Log.
Source: Q2 2026 Report (Final for Approval, v3), Section 7 and Table 12 (progress text). Status colours originally recovered from the Rev 1.5.3 PDF, pages 34–43; v3 cell shading matched for all 44 milestones per the Stage 1 Reconciliation Matrix. Position as at 30 June 2026.
Core Indicators
The Core Indicators are a standardised set of quantitative and qualitative metrics within the JET IP monitoring and evaluation framework, used to track the performance, progress and outcomes of projects in the Investments Register. They provide consistent, comparable data across diverse project portfolios and act as a proxy for expected outcomes across the JET IP.
Coverage limitation — read before interpreting any result on this tab
The Q2 2026 reporting base consists of 31 projects from three contributing partners, representing approximately 11.7% of the 266 projects in the JET Investments Register.
These results do not represent the full JET portfolio. The sample remains limited and non-representative, and the evidence should be understood as an emerging reporting base that will expand as further submissions are received.
Reporting base
Contributing partners
Register coverage
Indicator families
Reporting coverage by indicator family
Proportion of the 31 reporting projects submitting data on each indicator
Percentages indicate the proportion of the 31 reporting projects that submitted data on each indicator — not the proportion of the 266-project Register. Not all JET projects are relevant to all five Core Indicators; projects report only on those relevant to them.
Core Indicator position as at 30 June 2026
Qualifications that apply to every figure above
Results are self-reported and have not been independently verified. Reporting periods vary across interventions. Quarterly reporting is not compulsory for JET partners; submitters report according to their existing reporting schedules.
Planned and actual figures are kept separate. Headcount opportunities are not combined with FTE jobs. Lifecycle emissions estimates are not aggregated with annual emissions reductions. Where a submission did not provide a clear measurement unit, performance rating or evidence of achieved change, the result is qualified or excluded from aggregation.
Findings on Institutional Strengthening are largely based on self-reported ordinal assessments and should be interpreted as evidence of enabling institutional change rather than independently verified institutional performance. The quality and depth of community engagement cannot be inferred from the numeric level alone.
Source: Rev 1.5.3, Section 8, Tables 13 and 14, and the Interpretation sub-section.
Impact Indicators
Building a credible measurement base
Work during the quarter ending 30 June 2026 remained foundational: aligning the Impact Indicators with South Africa's official statistical architecture and establishing what can be reported, at what level and at what frequency. The position was subsequently validated against the Statistics South Africa indicator submission dated 3 August 2026.
The alignment work is advanced but not complete. Integration into routine statistical production should not be assumed.
Level 1 — Overall readiness
Indicators assessed
Mapped to IIF or comparator
Black-classified
Have data or a potential source
Levels 2 and 3 — Alignment and availability
Mapping and availability are separate assessments. Availability cannot be inferred from whether an indicator has an IIF match, and mapping cannot be inferred from whether values exist.
Levels 4 and 5 — Explore the 62-indicator framework
Select a band on the availability bar to filter, or use the controls below. Select any indicator to open its detail. Source: Annexure A, Tables A2 and A3, drawn from the Stats SA workbook submitted 3 August 2026.
Methodological controls that apply to every value above
Mapping is not equivalence
Mapping to the IIF or a closest comparator does not denote exact indicator equivalence, identical definition, methodology, unit of measurement, disaggregation or reference period. An indicator-by-indicator metadata review is still required before matches can be confirmed.
Black does not mean current or exact
A black classification does not necessarily mean a current-quarter observation exists, that the value is a perfect match to the JET indicator, or that the data is directly comparable without qualification. Much of the available information is annual, historically lagged or published at national level only. Provincial disaggregation is not consistently available.
Comparators and proxies are labelled
An IIF indicator is already included in Stats SA's framework. A closest available comparator is an existing official measure related to, but not exactly corresponding with, the JET indicator. A potential proxy is a substitute measure. These categories remain distinct wherever a value is presented; a comparator value is never presented as though it were the JET indicator itself.
Missing data is not generated
No missing indicator value is interpolated, estimated or inferred anywhere in this dashboard. Data predating 2022 is treated as baseline information, JET IP implementation having commenced in 2022. Q1 2026 is used for unemployment because Q2 labour market results had not been published at the cut-off.
Completeness control — 17 black, 14 populated
The “Jet Indicators” worksheet classifies 17 indicators as black. The “Data values” worksheet contains populated numeric values for only 14 of them.
For 3.5.2b and 3.5.3, comparator and disaggregation rows are present but the numeric cells are blank. 4.2.4a has no corresponding row at all. These three indicators retain their black classification, and are shown in the explorer above as having no populated numeric value in the source. No value has been invented.
The eight unaligned indicators are not identified
The report provides the 54 mapped / 8 not aligned result at aggregate level only. The submitted workbook does not expose an indicator-by-indicator mapping-status field for all 62 indicators. Annexure A therefore does not infer which individual indicators constitute the unmatched eight, and neither does this dashboard. No reverse-engineered or inferred mapping classification appears anywhere in the explorer above.
Forward work programme
- Completing the indicator-by-indicator metadata review
- Assessing definition and methodology differences between JET indicators and their IIF comparators
- Continuing to confirm the suitability and availability of the required disaggregation
- Continuing engagement with the identified data custodians
- Continuing work to strengthen administrative data quality within the National Statistics System
- Maintaining a regular quarterly reporting and validation cycle with Stats SA
- Continuing to maintain and extend Annexure A and the underlying source dataset
- Holding the planned workshop to review and rationalise the JET Impact Indicators
Items marked with an information symbol are continuing processes and are not expected to be completed within the quarter ending 30 September 2026. They will remain open until the associated data gaps have been closed. Administrative and third-party data require fit-for-purpose quality assurance before public reporting; assessment aligned to SASQAF may be appropriate, and no such assessment has been completed to date. No Impact Indicator material is published without the prior sight and agreement of Stats SA.
Source: Rev 1.5.3, Section 9, Table 15 and Annexure A (Tables A1, A2 and A3). Underlying dataset: “JET_Indicators_3 August2026.xlsx” as described in the report.
Evaluations
The 2026 JET IP evaluation programme comprises one formative evaluation and three rapid diagnostic evaluations. This tab reports the process stage reached at 30 June 2026 for each, and the position of the programme as a whole.
Evaluation portfolio overview
Period control
At 30 June 2026 the evaluation programme was still at various terms of reference, publication, proposal, procurement, review and preparatory stages. No evaluation had a completed procurement, an appointed evaluator, fieldwork underway, or a completed evaluation. Later procurement or appointment outcomes are outside the reporting period and are not represented here.
Where the four evaluations sit
Phase labels appear once, here. Each evaluation lane below carries a compact marker against the same five organising phases.
These five phases are dashboard organising categories used to position the evaluations relative to one another. They are not statuses drawn from the Q2 2026 Report, and they carry none of the Table 12 RAG colour semantics. An earlier organising phase is shown for context and progression only — it does not indicate that a phase, or the procurement process, has been completed. Each evaluation’s source-controlled current stage is stated in full as text in its lane.
The four evaluations
Related STO7 position. Table 12 records the 2026 milestone as at least four rapid diagnostic evaluations completed and published, each with a formal management response and improvement plan adopted, and the JET IP 2023–2027 Implementation Evaluation completed and published with recommendations for the JET IP 2028–2032. The Q2 progress statement records bids under evaluation, draft terms of reference prepared, and one RFP planned for publication in July 2026. The Municipalities technical assistance diagnostic evaluation terms of reference were completed for publishing, with the RFP planned for publication in July 2026 — after the reporting cut-off.
Source: Q2 2026 Report (Final for Approval, v3), Section 10 and Table 12 (STO7), with Section 2. Positions are stated as at 30 June 2026; anticipated contract awards are not represented as completed.
JET IP Quarterly Progress Dashboard · Q2 2026
Reporting period ending 30 June 2026 · Seventh quarterly progress report
Derived from the JET IP Quarterly Progress Report, Q2 2026 — Final for Approval (v3), not yet formally approved. All values reflect the position as at 30 June 2026 and do not incorporate later developments.
ZAR equivalents converted at USD 1 = ZAR 17.69, the currency-pair average for the quarter. Project-level ZAR values may retain the historical exchange rates applicable at closure.
Prepared by the JET Project Management Unit, The Presidency, Republic of South Africa.